How Do You Move Water 7.5km Across a Mine Site?

Moving water 7.5km across a mine site takes a complete system, not just a pump and a pipe. It takes years of dewatering experience and a fleet of pumps and ancillary items to match, all designed around the site’s specific requirements.

What Does a 7.5km Water Transfer System Involve?

When a client needed high flow water transfer across 7.5km of DN1000 pipeline to meet environmental requirements, Aquaflo Hire collabarated with design engineers to deliver a complete solution. It included –

  • Two pontoon mounted diesel pumpsets with manifold
  • 80 metres of walkway infrastructure
  • Onshore diesel storage
  • Automatic level controls
  • Scada network integration
Aquaflo Hire self bunded fuel cell

Why Does Long Distance Water Transfer need More Than a Pump and Pipe?

Over 7.5km, every part of the system has to work with the others. The pumps need stable, safe access. The fuel needs to be on hand. Water levels need to be managed automatically, and the site needs real world live information. Treating these as separate items creates challenges. Designing them as one system solves the problem.

What Was the Result

A user friendly solution, delivered on time and meeting all site and environmental compliance requirements.

This is what a complete water management solution looks like in practice. Not just off the shelf equipment on a truck, but a system designed around the site’s specific requirements.

Aquaflo Hire’s BDMs have the real world experience needed to design and supply dewatering solutions that really work. All backed up by one of Australia’s largest fleets of pumpsets and ancillary equipment. Talk to them about your water transfer needs. They love a challenge.

Categories

Similar Articles

Water cart on haul road
• 14/10/2026
Dust Control Compliance in 2026

Aquaflo Hire’s fleet includes truck fill points, sprinkler systems, evaporation fans and ancillary items for dust suppression at mines and quarries anywhere in Australia

Guests at Aquaflo Hire's Qld open day
• 18/08/2026
Our New Home. Your New Resource

Aquaflo Hire recently threw open the doors to our new Queensland facility at Coolum, and it was a ripper of a day. Over 80 attended and enjoyed live demonstrations, getting…

Australian weather synoptic with heavy rain band approaching east coast
• 06/08/2026
Should I Book a Dewatering Pumpset Before the Wet Season Arrives?

The short answer is yes. Once the rains arrive everyone wants to hire a pumpset. While we have one of Australia’s largest fleets of pumpsets and ancillary items available, it…

Contact Us

Aquaflo Enquiry Form